anyone know if the COGS on an invoice can be counted as a cost towards a project? it seems to appear but then get reversed (job costing)
k
KevinJ of Kansas
11/30/2020, 3:23 PM
if you are using the advanced project profitability reports - you need to pull out the inventory accounts (it hits both inventory and COGS - and therefore zeroes itself out) not sure why NS hasn't fixed this yet.
n
Nicolas Bean
11/30/2020, 3:23 PM
yeah I noticed that.. its weird
Nicolas Bean
11/30/2020, 3:24 PM
I found a workaround -> if you create a PO with the line as "billable" the invoice COGS works fine.. and then you can just close the PO
k
KevinJ of Kansas
11/30/2020, 3:24 PM
or you can update the profitability report to exclude the inventory line....