[ADJUSTING PO QUANTITIES] Guys, what is the best ...
# general
i
[ADJUSTING PO QUANTITIES] Guys, what is the best practice here? Situation
We raise a PO for 20 units of a certain item.
Down the road, we learn that only 15 will be shipped by supplier.
We want to have NS understand that now only 15
Alternatives:
1. *Adjust down* the item quantity?
2. *Split the line in two* - one with 15 units and the other with 5, maintaining the first open and closing the second?
3. Somethings else?
Help?
m
Will the other 5 be shipped later? in that case you can do a partial item receival for 15 items, and later do another item receivel for 5 items. you end up with 1 PO for 20 items, and 2 items receivals for combined 20 items
i
In this case, the other 5 items were cancelled by supplier
We will effectively receive only 15 units
s
If nothing is billed or shipped, then yes I would just change the PO to 15. If it's already been billed then you gotta do more wonky stuff.