Has anyone found a way to inactivate or stop time entry for just specific tasks on a project. SA gives only a solution for inactivating the entire project. However, we just want to stop time entry for specific tasks. #C298P0BCK #C29J1BPM3
s
Hi AI1, the 2 options I know of are: 1. Change task status to "Complete" 2. Mark as unbillable.
a
Hey that worked!! Not sure why I didn't think of that before. The task status was the way to go, thanks
Actually, I spoke too soon. It works for the Time related tasks, but if you have tasks related to just expenses then it doesn't help. We have a task for Labor time and a separate task for expenses and if you mark it closed you can still log expenses against that task. Bummer