Hey folks - We're exploring implementing resource allocations at our org... We've been poking around and I have 2 main questions that I'd love some insight on:
1. With generic resources, are you able to define an available allocation per day for a generic resource? For instance, if I have a generic resource for “designer” and I have 4 people that fill that role at the org, I would expect the available hours for that generic resource to be 32 hours per day (8 hours per day x 4 employees).
2. When it comes to an employee’s utilization, is there a way to specify a max utilization per day. In other words, a manager may only be available to work on projects for 4 hours a day. The obvious answer here is the “Target Utilization” field on the employee record, but remarkably this does not seem to have any impact on the resource allocation chart.
Appreciate any thoughts here!