Question: On projects, the resource employee rates...
# general
m
Question: On projects, the resource employee rates are 66.5% less than their labor rate on their employee record. What’s causing this and why? I’m a little fuzzy with projects.
k
you may have different source for rate on projects. Check Financial tab to see if customer rates are used. You may also have rates assigned on items which are used with resources on tasks
m
No luck. No customer rate, no special rate on the timesheet service item. I have no idea why it’s discounting.
k
so what do you have for rates other than the labor cost rates assigned to employees? you must use some rate, what is it?
there are default rate cards that projects come with, check those, see if that’s that.
l
are you using multi-currency? the labor rate on the projects may be in USD and the employee’s currency is in a lower type of currency
m
Figured it out. The exchange rate on the project was altering the resource cost by exactly that much.