Hi how to import project task with multiple resources without creating new task for each resource
p
Since the import process for project tasks is different (only create) you can’t use external ID to import one record with multiple ‘rows’ so instead you have to have multiple columns (resource 1, resource 2, resource 3, etc) and populate rate, service item, estimated work, etc for each. It’s a lot of columns, but better than hand entering the tasks. good luck!