Has anyone seen this error before (running rev pla...
# general
h
Has anyone seen this error before (running rev plan update after we updated an item to a POC rev rec rule and the amount source to project progress)? "Invalid revenuerecognitionrule reference key 8 for ispercentcomplete F." I know what rev rec rule is throwing the error but I'm not sure what record the "ispercentcomplete" flag is coming from. Nothing on the schema that I can see
k
this error is referred to the way your rev rec rule is set up for being used in %complete project rev rec. Another words, the rev rec rule is likely not set up correctly for % complete
h
Yeah we're going to re-run it. For posterity, the "ispercentcomplete" flag was on the Revenue Plan record.