How can you create a custom view on the Project Tasks/Milestones sublist that maintains the expand all/collapse all feature? For instance we have a Tracking view where Tasks can be expanded to see subtasks. Whenever I create a custom view, this feature is not available. Every subtask is listed under every Task.
s
sam1128
03/01/2019, 8:11 PM
Not possible last time I checked with Netsuite it was an enhancement.
sam1128
03/01/2019, 8:12 PM
Only 3 default sublists can be expanded or collapsed.
r
reptar
03/01/2019, 8:19 PM
great, thanks
reptar
03/01/2019, 8:28 PM
Do you know the other two sublists? Someone is asking.
j
James Morris
03/01/2019, 8:28 PM
@reptar If you only have two levels you could build a separate view for each level and just swap back and forth. Not really helpful if you have a whole bunch though 🤷
r
reptar
03/01/2019, 8:31 PM
NVM, it's Planning, Tracking and Variance I'm told.