Anyone know the logic/math behind the ‘Remaining’ ...
# projects
p
Anyone know the logic/math behind the ‘Remaining’ field on the Charges Summary tab? Field level help says ‘This is the total charge amount that has not been billed or put in the Ready stage.’ but the amount doesn’t equal any combination of charges on my project….
k
Check out the projects financial tab > Charges. This will list what is Pending. You can also view the fixed fee rules to see the charges that still need to be billed (and are not pending yet).
p
Okay...but this project from my screenshot does not have any fixed fee rules. I have forecast charges of $3,840 but I just can’t figure out where the other $2k is coming from. Might just be a data issue for this specific project...but it’s real real weird.