When you update the manufacturing Routing because of productivity increase, do you need to wait till you finish the current WO or effective date like Bill of Material?
a
Adam K
04/28/2021, 1:23 AM
Only Newly created work orders should pick up the updated routing. Also if your creating a new routing vs updating the current one would impact as on the Work Order the Routing is selected if not default for the assembly
s
Suitestallion
04/28/2021, 1:24 AM
If the work order is planned can I remove the item and reload the item to get new routing? Or that won’t help?
a
Adam K
04/28/2021, 1:24 AM
that should work yes
s
Suitestallion
04/28/2021, 1:26 AM
Got it but if the work order issue is already created then it’s a done deal. It’s not going to pick up the new routing
a
Adam K
04/28/2021, 1:27 AM
Yes if in progress, the planned Time won't update.