Anyone using the Work Order with Backward calculation. What are you solutions when it comes to the supply allocation feature? In testing, we’ve noticed that the Supply Required by Date for the work order (when the materials are required), is setting based on the production end date. Meaning, the raw materials are being sourced by the end of the production but not before production begins.
That could mean that a 3 day production on a work order won’t have the supplying materials until the day it is scheduled to be completed...
Have we missed something in our setup or is this a defect not currently considered in the feature?
NS support is taking their time coming back to us on this one...