hi all - i have supply planning set to auto-generate work orders in released status, but it is setting the production start date to 11/1/2020 (which is the supply order date from the demand plan), and the production end date to 10/31/2020 <-- anyone know what might be controlling this? i don't see this behavior when manually creating a WO for the item/location
al3xicon
10/13/2020, 10:30 PM
I had to set the Work Order Lead Time on the location level for this, that fixed it
k
KevinJ of Kansas
10/13/2020, 10:30 PM
I was just about to suggest looking at lead time
KevinJ of Kansas
10/13/2020, 10:30 PM
you beat me to it as I was starting to type
a
al3xicon
10/13/2020, 11:25 PM
ha - thanks! it makes sense but i haven't messed with auto-generated WOs from supply plans before
al3xicon
10/13/2020, 11:25 PM
that said, the fact that the option is there is really saving us for this particular use case