Is anyone using lead times with the demand plannin...
# manufacturing
z
Is anyone using lead times with the demand planning feature? If I have a work order with an assembly and that assembly has a lead time of five days it is taking that lead time and multiplying it by the quantity of the work order. I have like 3 different assembly items involved and each one has a lead time of five days so in reality I want the work order start date to be scheduled 15 days ahead of the completion date but instead it is 5 x 5 x 5 the quantity and really messing up the timing.