most of the module works well, but the scheduling is not working for us.
we cant plan sub assemblies of planned work orders (create work order from a "planned" work order) we have to release it first.
and then the finite scheduling does not work, as it handles planned and not released work orders.
also if we change a delivery date of a top level work order. it should reschedule all sub assemblies, but if there are too many (10-15+), it crashes (without telling you). and we have work order structurtes og 20-370 work orders in one tree. hopefully you dont.