I'm looking through our MRP exceptions. We have some errors for "Insufficient lead time for proposed Planned Purchase Order by 99 day(s)" from back in December (12/6/25) for 497 units. Looking under the supply tab there are no requests for 497. Doing a planned order search for the item shows nothing for December. Is it possible to clear out old exceptions, or track down which planned order is generating the error?
I can see 4651 units under late demand, and that matches the exception count. From my understanding MRP is only forward looking so past-due demand should drop off outside of the planning window. No?
Ended up figuring this out. It's generated based on the requirement date of the planned demand which is late since we won't meet it.