MRP question, i can't get consumption to work as expected. Example: we have weekly demand plans set on sunday
weekly demand plan for 11/2 = 521
orders so far for the week = 450
i would expect to see pending forecast of 71
my location settings are:
late days period: 7
past due forecast days: 6 (so 11/2 forcast stays valid all week)
backwards consumption: 6 (so all orders in throughout the week are consumed by 11/2 forecast)
forward consumption: 1 ( allowing orders for saturday to be consumed by the next week forecast but all other orders should go back to 11/2)
but for some reason i keep seeing that the actual demand = 71 which is correct these are the open orders for the week,
but i'm seeing pending forecast of 101? i just can't seem to wrap my head around what's going wrong here.