Hello all. I just switched over to WIP and Routing...
# accounting
a
Hello all. I just switched over to WIP and Routing and it looks like my PLanned Cost for Machine Run time is getting pulled into the GL report. Wondering if anyone can help me fix this error
b
the planned cost revaluation record?
a
when I create a Work Order Completion it is pulling our Planned Cost numbers when I look at the GL
b
What number would you want instead?
a
the Actual cost numbers
b
You use standard cost right?
a
I believe so yes. Where would I go to verify? Sorry if its a dumb question I came in a year ago and still getting my feet wet with the accounting side
b
You use the word planned cost so you must. This is how it works, the item is cost rolled and the standard cost is set, then that cost is used for transactions and valuating inventory on hand