but even with supply demand if you need to make item X with 70 components you will need to enter them right? or you are saying in demand planning it will create PO automatically with those items required
h
normally components will go on multiple assemblies and companies would want to buy components all at once for vendors not specifically for a specific assembly
therefore this option doesn't exist in NS. However for certain businesses (i'm assuming each assembly of yours is pretty custom and a spot buy) then yes it would make sense to develop a solution for this
One option is to utilize the "Item Group" functionality and import the components of your assembly into the group. That way you can select an item group and all of the componetns will list on the PO
if you have multiple vendors for the 70 components you would have to have one group listing all components you are buying from that vendor and a seperate group for another vendor
another option
theoretically if you are not using demand planning you can set the items to "reorder point" on item record, then use the "order Items" screen to create PO's. if the Work orders are in the system the components will have a demand to them, so all of the items on the work order will display on that screen (provided you do not have enough on hand). You can then set preferred vendors for each item and you can mass add itemes to the PO per each vendor
s
Thanks @Howard item group was what I was looking for didn’t think about that, will run that options and see how they want to go about, we do have demand planning but like you said we can also use reorder point , I think I have enough ammo for next week 😀