any chance possible can i bypass this error message? We don't really use the production end date field on work orders. any down stream issues i should know about? I was thinking to have a workflow auto populate it to todays date to bypass it for now. what happens if i have the end date as 7/14/25 but i work on the work order 7/15 or a week from today?
b
There is a setting in manufacturing settings to set start / end date automatically based on work order lead times
u
does the end date have any impact to inventory?
b
No it is really just a byproduct of planning times
m
The end date is calculated from the assembly routing time. Maybe you don’t use routings? Otherwise you can use a set field value action in a workflow to set end date based on whatever logic you need