Hi everyone, I have a question. While saving a wor...
# general
v
Hi everyone, I have a question. While saving a work order, I am encountering the following error: "Error: '<Work Center>' assigned to '<Manufacturing Cost Template>' cannot have more than 260 planned time entries. Reduce estimated work or increase units for the resource." Can anyone explain why I am getting this error and how to resolve it? Any help would be greatly appreciated!
j
Based on the both the Machine resources & Labor resources (Lists/Relationship/Groups - Manufacturing Work Center flag set to true ) of the Manufacturing Work Center & the manufacturing routing(s) with Setup time & run rate with that group assigned.