Is it possible to have MRP generate the Work Order...
# demandplanning
b
Is it possible to have MRP generate the Work Orders, rather than a planned work order?
a
No, you need to generate the work orders from Planned Work orders. The reason for Planned work orders is to allow the supply planners to review the WOs before committing.
👍 1
r
I'd double check the Manufacturing Preference > Create Work Orders in Supply Planning. This may have been the old supply planning but I'm not sure if this impacts the Planning Workbench. However, it sounds like a disaster depending on your planning horizon
n
If I am understanding the question - yes this is possible with a Suitelet. Once the WO is created by the Suitelet (can be bulk operation as well) the Planned Work Order is cleared after re-running the repository. Problem Solved.