Question…. using the Cost variance analysis suiteapp and have entered Overhead and Consumable recovery lines in the BOM which have cost category and associated costs. When viewing the costed BOM they are valued. However when run a cost variance analysis report they appear as 0.00 Planned and 0.00 Actual costs. any suggestions on the setup changes or why this may occur.. value appears to be included in standard cost and therefore posted to the GL..