Projects - I am looking to uncheck "limit time and expenses to resources", when i save the record it keep selecting even if i un select it. in system note the action is not written and there is no workflow or script running, what it could be?
k
Karina
06/28/2023, 5:44 PM
there are other checkboxes that relate to this functionality such as Allow Allocated resources to enter time for all tasks. you need to uncheck that box firs to uncheck the one you need. honestly, it is easier to make every employee as a resource. and if you uncheck you won’t be able to use vendors as resources.
👍 1
o
ofer.e
07/03/2023, 8:27 AM
i did some tests for that, but same result, it always keep to be selected